Within the contractual works, we finished the ground floor, partially the first and second basement of the Diagnostic-Therapy Service, and the construction of a new traffic terminal with the finalization of the ground floor, first and the second basement. Nearby, we also built a new laboratory for the requirements of emergency medical assistance and external arrangement of the traffic terminal and the surrounding of the Polyclinic. We built-in almost 6,900 m3 of concrete and 5,010 m2 of various paving stones. Due to the technological demands of the building, we used the most advanced techniques of planning and BIM modeling of the building.

Deadline for completion of work: April 2017

Value of performed works: €22 million

 